Mon and Wed updates
Its been a pretty busy week so far.
- Primed and painted the firewall braces.
- Shortened the fuel rail return hose to the FPR
- Re-installed the fuel pressure gauge sender (I still need a hole plug for the FPR gauge port that is unused)
- Finished the cold side charge pipe – cut out the hole for the BOV (I always cut and port them after welding) and beaded the ends.
- Installed the BOV and the vaccum line (complete with a nice Oettiker clamp)
- Removed, welded shut, and ground smooth a notch in the valve cover – previously there for TB clearance on the old setup
- Also cleaned up the welds on the valve cover, repainted it and drilled holes for the press in studs (to mount the coils assembly onto)
Before After - Finished up the Megasquirt mods. Added a peak and hold driver board for the injectors and a coil driver board inside the top cover. To make more room for the boards and two new connectors for Spark and Fuel I extended the sides and ends of the case. Also added functionality for boost control, IAC drive, and launch/flat shift control.
- Painted and installed the firewall blockoff / wire connector bulkhead panel. I used some foam gasket tape around the edges so it can be removed easily and still seal.
- Re-routed the wiper motor wires to the new bulkhead connector
- Finished removing the leftover HVAC blower wiring
- Installed the main Megasquirt engine harness and the coil and injector harnesses.
- Re-routed the boost gauge tube to the new bulkhead area. I still need to install the bulkhead feed-thru fitting.
I think that is it for this week so far. I’m sure I forgot something. I shouldnt skip an update.
Dan
-